Procedure to Improve Execution Speed Through Optimized Planning with Lob, Lps and Bim Methods in a Multifamily Building in Metropolitan Lima

Descripción del Articulo

As a developing country, Peru has great limitations in the application of new and innovative technologies in the construction sector. Construction projects consist of several stages in their development, one of the most important is the planning stage, which is essential to achieve efficient executi...

Descripción completa

Detalles Bibliográficos
Autores: Pereda, Nicholas, Ríos, Jairo, Ulloa, Karem
Formato: artículo
Fecha de Publicación:2025
Institución:Universidad Peruana de Ciencias Aplicadas
Repositorio:UPC-Institucional
Lenguaje:inglés
OAI Identifier:oai:repositorioacademico.upc.edu.pe:10757/683813
Enlace del recurso:http://hdl.handle.net/10757/683813
Nivel de acceso:acceso embargado
Materia:BIM
Buildings
Construction
LOB
LPS
Planning
Speed
Descripción
Sumario:As a developing country, Peru has great limitations in the application of new and innovative technologies in the construction sector. Construction projects consist of several stages in their development, one of the most important is the planning stage, which is essential to achieve efficient execution and meet established deadlines. However, this stage is usually tedious and complicated to carry out since there are multiple factors that can affect the estimates obtained from the planning process. However, the deadlines for the execution of construction projects are tight and failure to comply generates large losses of money. That is why this article seeks to implement the Lines of Balance (LOB), Last Planner System (LPS) and Building Information Modeling (BIM) methodologies to the traditional procedure. First, surveys were conducted on three different construction projects to determine the traditional planning process. Secondly, a procedure is developed to integrate the 3 aforementioned methodologies. Finally, the process was applied in a building project. A comparative analysis was carried out between the current state of the project and the state after using the aforementioned procedure. As a result, execution speeds increased for the items that maintained the same amount of work, the amount of m3 of slab emptying increased by 33.33%. It was observed that in the planning and work execution phase, the procedure improves the speed of execution of the items.
Nota importante:
La información contenida en este registro es de entera responsabilidad de la institución que gestiona el repositorio institucional donde esta contenido este documento o set de datos. El CONCYTEC no se hace responsable por los contenidos (publicaciones y/o datos) accesibles a través del Repositorio Nacional Digital de Ciencia, Tecnología e Innovación de Acceso Abierto (ALICIA).