“mejoramiento de los indicadores de avance por incremento de la longitud de perforación de 6 a 8 pies, aplicando voladura controlada con accesorios no eléctricos de retardo en la mina de la compañía minera poderosa s.a.”

Descripción del Articulo

Compania Minera Poderosa SA He has been conducting operations in the ore deposits in the RA2120 section of 4.5 x 4.5 m in Nv. 2120 San Francisco Lode mine Pataz. Reservoir characteristics are irregular, being unstable areas, qualifying as rock MF / P (much fractured poor soil), generating sobrerotur...

Descripción completa

Detalles Bibliográficos
Autores: Aguilar Contreras, Efraín Humberto, Vera Quispe, Fermín
Formato: tesis de grado
Fecha de Publicación:2016
Institución:Universidad Nacional de Trujillo
Repositorio:UNITRU-Tesis
Lenguaje:español
OAI Identifier:oai:dspace.unitru.edu.pe:20.500.14414/3853
Enlace del recurso:https://hdl.handle.net/20.500.14414/3853
Nivel de acceso:acceso abierto
Materia:Mejoramiento de los indicadores de avance por incremento de la longitud de perforación
id UNIT_b931eca4ab071c06fb675bb94fc30697
oai_identifier_str oai:dspace.unitru.edu.pe:20.500.14414/3853
network_acronym_str UNIT
network_name_str UNITRU-Tesis
repository_id_str 4801
dc.title.es_ES.fl_str_mv “mejoramiento de los indicadores de avance por incremento de la longitud de perforación de 6 a 8 pies, aplicando voladura controlada con accesorios no eléctricos de retardo en la mina de la compañía minera poderosa s.a.”
title “mejoramiento de los indicadores de avance por incremento de la longitud de perforación de 6 a 8 pies, aplicando voladura controlada con accesorios no eléctricos de retardo en la mina de la compañía minera poderosa s.a.”
spellingShingle “mejoramiento de los indicadores de avance por incremento de la longitud de perforación de 6 a 8 pies, aplicando voladura controlada con accesorios no eléctricos de retardo en la mina de la compañía minera poderosa s.a.”
Aguilar Contreras, Efraín Humberto
Mejoramiento de los indicadores de avance por incremento de la longitud de perforación
title_short “mejoramiento de los indicadores de avance por incremento de la longitud de perforación de 6 a 8 pies, aplicando voladura controlada con accesorios no eléctricos de retardo en la mina de la compañía minera poderosa s.a.”
title_full “mejoramiento de los indicadores de avance por incremento de la longitud de perforación de 6 a 8 pies, aplicando voladura controlada con accesorios no eléctricos de retardo en la mina de la compañía minera poderosa s.a.”
title_fullStr “mejoramiento de los indicadores de avance por incremento de la longitud de perforación de 6 a 8 pies, aplicando voladura controlada con accesorios no eléctricos de retardo en la mina de la compañía minera poderosa s.a.”
title_full_unstemmed “mejoramiento de los indicadores de avance por incremento de la longitud de perforación de 6 a 8 pies, aplicando voladura controlada con accesorios no eléctricos de retardo en la mina de la compañía minera poderosa s.a.”
title_sort “mejoramiento de los indicadores de avance por incremento de la longitud de perforación de 6 a 8 pies, aplicando voladura controlada con accesorios no eléctricos de retardo en la mina de la compañía minera poderosa s.a.”
author Aguilar Contreras, Efraín Humberto
author_facet Aguilar Contreras, Efraín Humberto
Vera Quispe, Fermín
author_role author
author2 Vera Quispe, Fermín
author2_role author
dc.contributor.advisor.fl_str_mv Prado Palomino, Pedro
dc.contributor.author.fl_str_mv Aguilar Contreras, Efraín Humberto
Vera Quispe, Fermín
dc.subject.es_ES.fl_str_mv Mejoramiento de los indicadores de avance por incremento de la longitud de perforación
topic Mejoramiento de los indicadores de avance por incremento de la longitud de perforación
description Compania Minera Poderosa SA He has been conducting operations in the ore deposits in the RA2120 section of 4.5 x 4.5 m in Nv. 2120 San Francisco Lode mine Pataz. Reservoir characteristics are irregular, being unstable areas, qualifying as rock MF / P (much fractured poor soil), generating sobrerotura and damage to the crown, and increase the percentage of dilution. The operation is carried out in a conventional manner and are checked overconsumption of explosives, which is reflected in the so-called load factor indicator. Other deficiencies relate to blasting explosive improper drill column instead of 66 % were carried more than 75 %, resulting on excavations and increased the cost of drilling and blasting. In drilling deviations in parallelism they are detected by the absence of guiding , taking the burden no uniform remains and becomes larger at the bottom of the bore , affecting the fracturing and expected progress , especially if the holes relief are shorter that production . Faced with this problem you had as a result unfavorable indicators such as: advance 1, 66 m / disp.; yield 0.49 m / hg.; load factor of 31.79 kg / m drilling and blasting costs at 311.65 US $ / m . To solve these problems a scheme research considered increasing the length drill 6 to 8 feet and applying controlled blasting using non-electric delay was designed accessories. As a result the following objectives were achieved: the progress increased from 1.66 to 2.05 m / disp .; the yield increased from 0.49 to 0.71 ; The so-called load factor decreased from 31.79 to 26.1 kg / m and decreased the cost of drilling and blasting of US $ 311.65 to US $ 288.32 .
publishDate 2016
dc.date.accessioned.none.fl_str_mv 2016-10-20T17:05:58Z
dc.date.available.none.fl_str_mv 2016-10-20T17:05:58Z
dc.date.issued.fl_str_mv 2016
dc.type.es_ES.fl_str_mv info:eu-repo/semantics/bachelorThesis
format bachelorThesis
dc.identifier.uri.none.fl_str_mv https://hdl.handle.net/20.500.14414/3853
url https://hdl.handle.net/20.500.14414/3853
dc.language.iso.es_ES.fl_str_mv spa
language spa
dc.relation.ispartof.fl_str_mv SUNEDU
dc.relation.ispartofseries.none.fl_str_mv TMI;
dc.rights.es_ES.fl_str_mv info:eu-repo/semantics/openAccess
dc.rights.uri.none.fl_str_mv http://creativecommons.org/licenses/by-nc-nd/2.5/pe/
eu_rights_str_mv openAccess
rights_invalid_str_mv http://creativecommons.org/licenses/by-nc-nd/2.5/pe/
dc.publisher.none.fl_str_mv Universidad Nacional de Trujillo
publisher.none.fl_str_mv Universidad Nacional de Trujillo
dc.source.es_ES.fl_str_mv Universidad Nacional de Trujillo
Repositorio institucional - UNITRU
dc.source.none.fl_str_mv reponame:UNITRU-Tesis
instname:Universidad Nacional de Trujillo
instacron:UNITRU
instname_str Universidad Nacional de Trujillo
instacron_str UNITRU
institution UNITRU
reponame_str UNITRU-Tesis
collection UNITRU-Tesis
bitstream.url.fl_str_mv https://dspace.unitru.edu.pe/bitstreams/3fc8b143-af9f-47ba-97f7-ee007edc199a/download
https://dspace.unitru.edu.pe/bitstreams/c2d2dcae-460a-4428-92fc-7ac5473f33f9/download
bitstream.checksum.fl_str_mv 8a4605be74aa9ea9d79846c1fba20a33
2e5dba857a5e9ced5202379e6bbb3f19
bitstream.checksumAlgorithm.fl_str_mv MD5
MD5
repository.name.fl_str_mv Repositorio Institucional - UNITRU
repository.mail.fl_str_mv repositorios@unitru.edu.pe
_version_ 1807289957138563072
spelling Prado Palomino, PedroAguilar Contreras, Efraín HumbertoVera Quispe, Fermín2016-10-20T17:05:58Z2016-10-20T17:05:58Z2016https://hdl.handle.net/20.500.14414/3853Compania Minera Poderosa SA He has been conducting operations in the ore deposits in the RA2120 section of 4.5 x 4.5 m in Nv. 2120 San Francisco Lode mine Pataz. Reservoir characteristics are irregular, being unstable areas, qualifying as rock MF / P (much fractured poor soil), generating sobrerotura and damage to the crown, and increase the percentage of dilution. The operation is carried out in a conventional manner and are checked overconsumption of explosives, which is reflected in the so-called load factor indicator. Other deficiencies relate to blasting explosive improper drill column instead of 66 % were carried more than 75 %, resulting on excavations and increased the cost of drilling and blasting. In drilling deviations in parallelism they are detected by the absence of guiding , taking the burden no uniform remains and becomes larger at the bottom of the bore , affecting the fracturing and expected progress , especially if the holes relief are shorter that production . Faced with this problem you had as a result unfavorable indicators such as: advance 1, 66 m / disp.; yield 0.49 m / hg.; load factor of 31.79 kg / m drilling and blasting costs at 311.65 US $ / m . To solve these problems a scheme research considered increasing the length drill 6 to 8 feet and applying controlled blasting using non-electric delay was designed accessories. As a result the following objectives were achieved: the progress increased from 1.66 to 2.05 m / disp .; the yield increased from 0.49 to 0.71 ; The so-called load factor decreased from 31.79 to 26.1 kg / m and decreased the cost of drilling and blasting of US $ 311.65 to US $ 288.32 .La Compañía Minera Poderosa S.A. viene realizando sus operaciones en los yacimientos minerales existentes en la RA2120 de sección de 4.5 x 4.5 m en el Nv. 2120 de la veta San francisco mina Pataz. Las características del yacimiento son irregulares, encontrándose zonas inestables, calificándose como roca MF/P (terreno muy fracturado pobre), generándose sobrerotura y daños en la corona, además de incrementar el porcentaje de la dilución. La explotación se realiza en forma convencional, habiéndose verificado un exceso de consumo de explosivos lo cual se refleja en el indicador conocido como factor de carga. Otras deficiencias en voladura se refieren a una inadecuada columna explosiva del taladro que en vez de 66% se les cargaba a más del 75%, originando sobre excavaciones y aumento en el costo de perforación y voladura. En perforación se detectaron desviaciones en el paralelismo, por ausencia de guiadores, teniéndose que el burden no se mantiene uniforme y resulta mayor al fondo del taladro, lo que afectaba el fracturamiento y el avance esperado, especialmente si los taladros de alivio son de menor longitud que los de producción. Ante esta problemática se tenía como consecuencia indicadores desfavorables como por ejemplo: avance 1,66 m/disp.; rendimiento 0,49 m/hg.; factor de carga 31,79 kg/m y costo de perforación de voladura en 311,65 US$/m. Para solucionar dichos problemas se diseñó un esquema de investigación que consideraba el incremento de la longitud del taladro de 6 a 8 pies y la aplicación de voladura controlada utilizando accesorios no eléctricos de retardo. Como resultados se lograron los siguientes objetivos: el avance aumentó de 1,66 a 2,05 m/disp.; el rendimiento aumentó de 0,49 a 0,71; El denominado factor de carga bajó de 31,79 a 26,1 kg/m, así como disminuyó el costo de perforación y voladura de US$ 311.65 a US$ 288,32. Palabras claves: Roca MF/P, veta, avance, rendimiento, factor de carga, costo de perforación de voladura, longitud de taladro, voladura controlada.spaUniversidad Nacional de TrujilloTMI;SUNEDUinfo:eu-repo/semantics/openAccesshttp://creativecommons.org/licenses/by-nc-nd/2.5/pe/Universidad Nacional de TrujilloRepositorio institucional - UNITRUreponame:UNITRU-Tesisinstname:Universidad Nacional de Trujilloinstacron:UNITRUMejoramiento de los indicadores de avance por incremento de la longitud de perforación“mejoramiento de los indicadores de avance por incremento de la longitud de perforación de 6 a 8 pies, aplicando voladura controlada con accesorios no eléctricos de retardo en la mina de la compañía minera poderosa s.a.”info:eu-repo/semantics/bachelorThesisTítulo ProfesionalIngeniero de MinasMinasUniversidad Nacional de Trujillo.Facultad de IngenieríaLICENSElicense.txtlicense.txttext/plain; charset=utf-81748https://dspace.unitru.edu.pe/bitstreams/3fc8b143-af9f-47ba-97f7-ee007edc199a/download8a4605be74aa9ea9d79846c1fba20a33MD52ORIGINALAguilar contreras, Efraín Humberto, Fermín Vera Quispe.pdfAguilar contreras, Efraín Humberto, Fermín Vera Quispe.pdfMejoramiento de los indicadores de avance por incremento de la longitud de perforaciónapplication/pdf4982943https://dspace.unitru.edu.pe/bitstreams/c2d2dcae-460a-4428-92fc-7ac5473f33f9/download2e5dba857a5e9ced5202379e6bbb3f19MD5120.500.14414/3853oai:dspace.unitru.edu.pe:20.500.14414/38532017-11-15 12:18:40.896http://creativecommons.org/licenses/by-nc-nd/2.5/pe/info:eu-repo/semantics/openAccessopen.accesshttps://dspace.unitru.edu.peRepositorio Institucional - UNITRUrepositorios@unitru.edu.peTk9URTogUExBQ0UgWU9VUiBPV04gTElDRU5TRSBIRVJFClRoaXMgc2FtcGxlIGxpY2Vuc2UgaXMgcHJvdmlkZWQgZm9yIGluZm9ybWF0aW9uYWwgcHVycG9zZXMgb25seS4KCk5PTi1FWENMVVNJVkUgRElTVFJJQlVUSU9OIExJQ0VOU0UKCkJ5IHNpZ25pbmcgYW5kIHN1Ym1pdHRpbmcgdGhpcyBsaWNlbnNlLCB5b3UgKHRoZSBhdXRob3Iocykgb3IgY29weXJpZ2h0Cm93bmVyKSBncmFudHMgdG8gRFNwYWNlIFVuaXZlcnNpdHkgKERTVSkgdGhlIG5vbi1leGNsdXNpdmUgcmlnaHQgdG8gcmVwcm9kdWNlLAp0cmFuc2xhdGUgKGFzIGRlZmluZWQgYmVsb3cpLCBhbmQvb3IgZGlzdHJpYnV0ZSB5b3VyIHN1Ym1pc3Npb24gKGluY2x1ZGluZwp0aGUgYWJzdHJhY3QpIHdvcmxkd2lkZSBpbiBwcmludCBhbmQgZWxlY3Ryb25pYyBmb3JtYXQgYW5kIGluIGFueSBtZWRpdW0sCmluY2x1ZGluZyBidXQgbm90IGxpbWl0ZWQgdG8gYXVkaW8gb3IgdmlkZW8uCgpZb3UgYWdyZWUgdGhhdCBEU1UgbWF5LCB3aXRob3V0IGNoYW5naW5nIHRoZSBjb250ZW50LCB0cmFuc2xhdGUgdGhlCnN1Ym1pc3Npb24gdG8gYW55IG1lZGl1bSBvciBmb3JtYXQgZm9yIHRoZSBwdXJwb3NlIG9mIHByZXNlcnZhdGlvbi4KCllvdSBhbHNvIGFncmVlIHRoYXQgRFNVIG1heSBrZWVwIG1vcmUgdGhhbiBvbmUgY29weSBvZiB0aGlzIHN1Ym1pc3Npb24gZm9yCnB1cnBvc2VzIG9mIHNlY3VyaXR5LCBiYWNrLXVwIGFuZCBwcmVzZXJ2YXRpb24uCgpZb3UgcmVwcmVzZW50IHRoYXQgdGhlIHN1Ym1pc3Npb24gaXMgeW91ciBvcmlnaW5hbCB3b3JrLCBhbmQgdGhhdCB5b3UgaGF2ZQp0aGUgcmlnaHQgdG8gZ3JhbnQgdGhlIHJpZ2h0cyBjb250YWluZWQgaW4gdGhpcyBsaWNlbnNlLiBZb3UgYWxzbyByZXByZXNlbnQKdGhhdCB5b3VyIHN1Ym1pc3Npb24gZG9lcyBub3QsIHRvIHRoZSBiZXN0IG9mIHlvdXIga25vd2xlZGdlLCBpbmZyaW5nZSB1cG9uCmFueW9uZSdzIGNvcHlyaWdodC4KCklmIHRoZSBzdWJtaXNzaW9uIGNvbnRhaW5zIG1hdGVyaWFsIGZvciB3aGljaCB5b3UgZG8gbm90IGhvbGQgY29weXJpZ2h0LAp5b3UgcmVwcmVzZW50IHRoYXQgeW91IGhhdmUgb2J0YWluZWQgdGhlIHVucmVzdHJpY3RlZCBwZXJtaXNzaW9uIG9mIHRoZQpjb3B5cmlnaHQgb3duZXIgdG8gZ3JhbnQgRFNVIHRoZSByaWdodHMgcmVxdWlyZWQgYnkgdGhpcyBsaWNlbnNlLCBhbmQgdGhhdApzdWNoIHRoaXJkLXBhcnR5IG93bmVkIG1hdGVyaWFsIGlzIGNsZWFybHkgaWRlbnRpZmllZCBhbmQgYWNrbm93bGVkZ2VkCndpdGhpbiB0aGUgdGV4dCBvciBjb250ZW50IG9mIHRoZSBzdWJtaXNzaW9uLgoKSUYgVEhFIFNVQk1JU1NJT04gSVMgQkFTRUQgVVBPTiBXT1JLIFRIQVQgSEFTIEJFRU4gU1BPTlNPUkVEIE9SIFNVUFBPUlRFRApCWSBBTiBBR0VOQ1kgT1IgT1JHQU5JWkFUSU9OIE9USEVSIFRIQU4gRFNVLCBZT1UgUkVQUkVTRU5UIFRIQVQgWU9VIEhBVkUKRlVMRklMTEVEIEFOWSBSSUdIVCBPRiBSRVZJRVcgT1IgT1RIRVIgT0JMSUdBVElPTlMgUkVRVUlSRUQgQlkgU1VDSApDT05UUkFDVCBPUiBBR1JFRU1FTlQuCgpEU1Ugd2lsbCBjbGVhcmx5IGlkZW50aWZ5IHlvdXIgbmFtZShzKSBhcyB0aGUgYXV0aG9yKHMpIG9yIG93bmVyKHMpIG9mIHRoZQpzdWJtaXNzaW9uLCBhbmQgd2lsbCBub3QgbWFrZSBhbnkgYWx0ZXJhdGlvbiwgb3RoZXIgdGhhbiBhcyBhbGxvd2VkIGJ5IHRoaXMKbGljZW5zZSwgdG8geW91ciBzdWJtaXNzaW9uLgo=
score 13.977305
Nota importante:
La información contenida en este registro es de entera responsabilidad de la institución que gestiona el repositorio institucional donde esta contenido este documento o set de datos. El CONCYTEC no se hace responsable por los contenidos (publicaciones y/o datos) accesibles a través del Repositorio Nacional Digital de Ciencia, Tecnología e Innovación de Acceso Abierto (ALICIA).