Design proposal of a Maintenance Management System for the Company Pesquera Pacasmayo E.I.R.L.

Descripción del Articulo

The purpose of this research is to implement preventive maintenance using the tools of: Predictive Maintenance and Total Productive Maintenance (TPM) in the company Pesquera Pacasmayo E.I.R.L.; since, after identifying the constant problems in the production area, it was identified that the main cau...

Descripción completa

Detalles Bibliográficos
Autores: Cubas Rodríguez, Julio Cesar, Pretel Chigne, Lisbeth Paola, Quezada Ramos, Erick Daniel, Santamaría Loro, Carla Mercedes, Valencia Vargas, Nathaly Yasmin, Yépez Pérez, Amanda Yuxuha
Formato: objeto de conferencia
Fecha de Publicación:2021
Institución:Universidad Privada del Norte
Repositorio:UPN-Institucional
Lenguaje:español
OAI Identifier:oai:repositorio.upn.edu.pe:11537/31104
Enlace del recurso:https://hdl.handle.net/11537/31104
http://dx.doi.org/10.18687/LACCEI2021.1.1.57
Nivel de acceso:acceso abierto
Materia:Mantenimiento industrial
Productividad
Industria pesquera
Availability
Preventive maintenance
https://purl.org/pe-repo/ocde/ford#2.11.04
Descripción
Sumario:The purpose of this research is to implement preventive maintenance using the tools of: Predictive Maintenance and Total Productive Maintenance (TPM) in the company Pesquera Pacasmayo E.I.R.L.; since, after identifying the constant problems in the production area, it was identified that the main causes of these problems arise from deficiencies in maintenance. The study has a pre-experimental design, in which data collection techniques and instruments were used, specifically in the analysis of information on the company's production and maintenance processes. First, a diagnosis of these areas was carried out to identify the problems that directly affect productivity, in order to determine the maintenance tools to apply; then, the Mean Time Between Failures was found, considering the work data in real time and the number of failures, finding the value of 40 hours for the main machine, 70.94 hours for the hydraulic generator and 54.36 hours for the refrigeration compressor; Average Time Between Repairs, considering the data on the downtime due to breakdown and the number of breakdowns, where the value of 5 hours was found for the main machine, 3.5 hours for the hydraulic generator, and 4 hours for the refrigeration compressor. Regarding availability, 89% was found for the main machine, 95% for hydraulic generators and 93% for refrigeration compressors. Similarly, preventive maintenance was applied to minimize these problems. Total Productive Maintenance (TPM) was also applied, where an increase in productivity is reflected; as well as, an increase of the Total Effectiveness of the team to 15%.
Nota importante:
La información contenida en este registro es de entera responsabilidad de la institución que gestiona el repositorio institucional donde esta contenido este documento o set de datos. El CONCYTEC no se hace responsable por los contenidos (publicaciones y/o datos) accesibles a través del Repositorio Nacional Digital de Ciencia, Tecnología e Innovación de Acceso Abierto (ALICIA).