Optimization of the control process in residential buildings using technological tools

Descripción del Articulo

Many construction companies worldwide continue to implement different methodologies to optimize time and improve management in the execution of works; however, a lack of control in projects continues to be observed. For this reason, one of the most common problems currently is the incompletion of sc...

Descripción completa

Detalles Bibliográficos
Autores: Prat, Joaquin, Romero, Alvaro, Rodriguez, Sandra, Farje, Julio
Formato: artículo
Fecha de Publicación:2020
Institución:Universidad Peruana de Ciencias Aplicadas
Repositorio:UPC-Institucional
Lenguaje:inglés
OAI Identifier:oai:repositorioacademico.upc.edu.pe:10757/656567
Enlace del recurso:http://hdl.handle.net/10757/656567
Nivel de acceso:acceso embargado
Materia:Management
Optimization
Plan Grid
Power Bi
Project
Subcontractors
Time
id UUPC_61c202ffc66f099043ff71b5843b6d3b
oai_identifier_str oai:repositorioacademico.upc.edu.pe:10757/656567
network_acronym_str UUPC
network_name_str UPC-Institucional
repository_id_str 2670
dc.title.en_US.fl_str_mv Optimization of the control process in residential buildings using technological tools
title Optimization of the control process in residential buildings using technological tools
spellingShingle Optimization of the control process in residential buildings using technological tools
Prat, Joaquin
Management
Optimization
Plan Grid
Power Bi
Project
Subcontractors
Time
title_short Optimization of the control process in residential buildings using technological tools
title_full Optimization of the control process in residential buildings using technological tools
title_fullStr Optimization of the control process in residential buildings using technological tools
title_full_unstemmed Optimization of the control process in residential buildings using technological tools
title_sort Optimization of the control process in residential buildings using technological tools
author Prat, Joaquin
author_facet Prat, Joaquin
Romero, Alvaro
Rodriguez, Sandra
Farje, Julio
author_role author
author2 Romero, Alvaro
Rodriguez, Sandra
Farje, Julio
author2_role author
author
author
dc.contributor.author.fl_str_mv Prat, Joaquin
Romero, Alvaro
Rodriguez, Sandra
Farje, Julio
dc.subject.en_US.fl_str_mv Management
Optimization
Plan Grid
Power Bi
Project
Subcontractors
Time
topic Management
Optimization
Plan Grid
Power Bi
Project
Subcontractors
Time
description Many construction companies worldwide continue to implement different methodologies to optimize time and improve management in the execution of works; however, a lack of control in projects continues to be observed. For this reason, one of the most common problems currently is the incompletion of scheduled work. Due to this, it is necessary to keep better control of the projects at the execution stage so that the contractor can optimally, quickly, and easily manage the progress of all the specialties involved. In this sense, this research develops the use of the Plan Grid Application for data collection in the field and the Power Bi software for the automatic processing and information visualization through a management dashboard where indicators are shown to reflect the progress and actual performance of the activities as well as the main non-compliance causes, which leads to optimize the control process and the time spent by its administrators to carry out this management.
publishDate 2020
dc.date.accessioned.none.fl_str_mv 2021-06-22T14:26:07Z
dc.date.available.none.fl_str_mv 2021-06-22T14:26:07Z
dc.date.issued.fl_str_mv 2020-09-30
dc.type.en_US.fl_str_mv info:eu-repo/semantics/article
format article
dc.identifier.doi.none.fl_str_mv 10.1109/CONIITI51147.2020.9240343
dc.identifier.uri.none.fl_str_mv http://hdl.handle.net/10757/656567
dc.identifier.journal.en_US.fl_str_mv 2020 Congreso Internacional de Innovacion y Tendencias en Ingenieria, CONIITI 2020 - Conference Proceedings
dc.identifier.eid.none.fl_str_mv 2-s2.0-85096535379
dc.identifier.scopusid.none.fl_str_mv SCOPUS_ID:85096535379
dc.identifier.isni.none.fl_str_mv 0000 0001 2196 144X
identifier_str_mv 10.1109/CONIITI51147.2020.9240343
2020 Congreso Internacional de Innovacion y Tendencias en Ingenieria, CONIITI 2020 - Conference Proceedings
2-s2.0-85096535379
SCOPUS_ID:85096535379
0000 0001 2196 144X
url http://hdl.handle.net/10757/656567
dc.language.iso.en_US.fl_str_mv eng
language eng
dc.relation.url.en_US.fl_str_mv https://ieeexplore.ieee.org/document/9240343
dc.rights.en_US.fl_str_mv info:eu-repo/semantics/embargoedAccess
eu_rights_str_mv embargoedAccess
dc.format.en_US.fl_str_mv application/html
dc.publisher.en_US.fl_str_mv Institute of Electrical and Electronics Engineers Inc.
dc.source.none.fl_str_mv reponame:UPC-Institucional
instname:Universidad Peruana de Ciencias Aplicadas
instacron:UPC
instname_str Universidad Peruana de Ciencias Aplicadas
instacron_str UPC
institution UPC
reponame_str UPC-Institucional
collection UPC-Institucional
dc.source.journaltitle.none.fl_str_mv 2020 Congreso Internacional de Innovacion y Tendencias en Ingenieria, CONIITI 2020 - Conference Proceedings
bitstream.url.fl_str_mv https://repositorioacademico.upc.edu.pe/bitstream/10757/656567/1/license.txt
bitstream.checksum.fl_str_mv 8a4605be74aa9ea9d79846c1fba20a33
bitstream.checksumAlgorithm.fl_str_mv MD5
repository.name.fl_str_mv Repositorio académico upc
repository.mail.fl_str_mv upc@openrepository.com
_version_ 1837188371824246784
spelling ebe59639da5503587f897f44e14e219730027fc2b34641b0b1d6619ed06a6139a2e500a19bdd30cc46071b55788ba9dcd3e8a1500db3156e7a0e707f54efe72b83fa8323c500Prat, JoaquinRomero, AlvaroRodriguez, SandraFarje, Julio2021-06-22T14:26:07Z2021-06-22T14:26:07Z2020-09-3010.1109/CONIITI51147.2020.9240343http://hdl.handle.net/10757/6565672020 Congreso Internacional de Innovacion y Tendencias en Ingenieria, CONIITI 2020 - Conference Proceedings2-s2.0-85096535379SCOPUS_ID:850965353790000 0001 2196 144XMany construction companies worldwide continue to implement different methodologies to optimize time and improve management in the execution of works; however, a lack of control in projects continues to be observed. For this reason, one of the most common problems currently is the incompletion of scheduled work. Due to this, it is necessary to keep better control of the projects at the execution stage so that the contractor can optimally, quickly, and easily manage the progress of all the specialties involved. In this sense, this research develops the use of the Plan Grid Application for data collection in the field and the Power Bi software for the automatic processing and information visualization through a management dashboard where indicators are shown to reflect the progress and actual performance of the activities as well as the main non-compliance causes, which leads to optimize the control process and the time spent by its administrators to carry out this management.application/htmlengInstitute of Electrical and Electronics Engineers Inc.https://ieeexplore.ieee.org/document/9240343info:eu-repo/semantics/embargoedAccessManagementOptimizationPlan GridPower BiProjectSubcontractorsTimeOptimization of the control process in residential buildings using technological toolsinfo:eu-repo/semantics/article2020 Congreso Internacional de Innovacion y Tendencias en Ingenieria, CONIITI 2020 - Conference Proceedingsreponame:UPC-Institucionalinstname:Universidad Peruana de Ciencias Aplicadasinstacron:UPCLICENSElicense.txtlicense.txttext/plain; charset=utf-81748https://repositorioacademico.upc.edu.pe/bitstream/10757/656567/1/license.txt8a4605be74aa9ea9d79846c1fba20a33MD51false10757/656567oai:repositorioacademico.upc.edu.pe:10757/6565672021-06-22 14:26:08.996Repositorio académico upcupc@openrepository.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
score 13.95948
Nota importante:
La información contenida en este registro es de entera responsabilidad de la institución que gestiona el repositorio institucional donde esta contenido este documento o set de datos. El CONCYTEC no se hace responsable por los contenidos (publicaciones y/o datos) accesibles a través del Repositorio Nacional Digital de Ciencia, Tecnología e Innovación de Acceso Abierto (ALICIA).