Reducing Subcontractor Progress Monitoring Time on Multifamily Building Finishes Using a BIM-Based Procedure
Descripción del Articulo
In multifamily project construction, specialty subcontracting is common, but monitoring subcontractors, especially during finishing, presents significant challenges due to manual methods that are time consuming, make it difficult to detect deviations, and result in cost overruns and delays. This res...
| Autores: | , , |
|---|---|
| Formato: | artículo |
| Fecha de Publicación: | 2025 |
| Institución: | Universidad Peruana de Ciencias Aplicadas |
| Repositorio: | UPC-Institucional |
| Lenguaje: | inglés |
| OAI Identifier: | oai:repositorioacademico.upc.edu.pe:10757/687659 |
| Enlace del recurso: | http://hdl.handle.net/10757/687659 |
| Nivel de acceso: | acceso abierto |
| Materia: | BIM Construction Monitoring time Progress monitoring Subcontractors https://purl.org/pe-repo/ocde/ford#2.01.00 |
| id |
UUPC_425d88dddbf9e185e66c39442da2be10 |
|---|---|
| oai_identifier_str |
oai:repositorioacademico.upc.edu.pe:10757/687659 |
| network_acronym_str |
UUPC |
| network_name_str |
UPC-Institucional |
| repository_id_str |
2670 |
| dc.title.es_PE.fl_str_mv |
Reducing Subcontractor Progress Monitoring Time on Multifamily Building Finishes Using a BIM-Based Procedure |
| title |
Reducing Subcontractor Progress Monitoring Time on Multifamily Building Finishes Using a BIM-Based Procedure |
| spellingShingle |
Reducing Subcontractor Progress Monitoring Time on Multifamily Building Finishes Using a BIM-Based Procedure Bazán, Darwin BIM Construction Monitoring time Progress monitoring Subcontractors https://purl.org/pe-repo/ocde/ford#2.01.00 |
| title_short |
Reducing Subcontractor Progress Monitoring Time on Multifamily Building Finishes Using a BIM-Based Procedure |
| title_full |
Reducing Subcontractor Progress Monitoring Time on Multifamily Building Finishes Using a BIM-Based Procedure |
| title_fullStr |
Reducing Subcontractor Progress Monitoring Time on Multifamily Building Finishes Using a BIM-Based Procedure |
| title_full_unstemmed |
Reducing Subcontractor Progress Monitoring Time on Multifamily Building Finishes Using a BIM-Based Procedure |
| title_sort |
Reducing Subcontractor Progress Monitoring Time on Multifamily Building Finishes Using a BIM-Based Procedure |
| author |
Bazán, Darwin |
| author_facet |
Bazán, Darwin Díaz, Leonardo Ulloa, Karem |
| author_role |
author |
| author2 |
Díaz, Leonardo Ulloa, Karem |
| author2_role |
author author |
| dc.contributor.author.fl_str_mv |
Bazán, Darwin Díaz, Leonardo Ulloa, Karem |
| dc.subject.es_PE.fl_str_mv |
BIM Construction Monitoring time Progress monitoring Subcontractors |
| topic |
BIM Construction Monitoring time Progress monitoring Subcontractors https://purl.org/pe-repo/ocde/ford#2.01.00 |
| dc.subject.ocde.es_PE.fl_str_mv |
https://purl.org/pe-repo/ocde/ford#2.01.00 |
| description |
In multifamily project construction, specialty subcontracting is common, but monitoring subcontractors, especially during finishing, presents significant challenges due to manual methods that are time consuming, make it difficult to detect deviations, and result in cost overruns and delays. This research proposes an automated monitoring procedure using a BIM model that integrates tools such as Revit, Navisworks, MS Project and Trimble Connect. The methodology includes four stages: analysis of information through surveys, identification of the traditional procedure in three companies, development of the new automated approach and validation in a pilot project. The results show a 42.4% reduction in daily monitoring time for subcontractors and a 41.4% reduction for technical personnel, in addition to improved access to real-time information. This optimizes coordination, reduces errors and ensures compliance with deadlines, significantly improving resource management in multifamily projects. |
| publishDate |
2025 |
| dc.date.accessioned.none.fl_str_mv |
2025-12-16T00:42:42Z |
| dc.date.available.none.fl_str_mv |
2025-12-16T00:42:42Z |
| dc.date.issued.fl_str_mv |
2025-01-01 |
| dc.type.es_PE.fl_str_mv |
info:eu-repo/semantics/article Other |
| format |
article |
| dc.identifier.doi.none.fl_str_mv |
10.11159/iccste25.189 |
| dc.identifier.uri.none.fl_str_mv |
http://hdl.handle.net/10757/687659 |
| dc.identifier.eissn.none.fl_str_mv |
23693002 |
| dc.identifier.journal.es_PE.fl_str_mv |
International Conference on Civil Structural and Transportation Engineering |
| dc.identifier.eid.none.fl_str_mv |
2-s2.0-105012222190 |
| dc.identifier.scopusid.none.fl_str_mv |
SCOPUS_ID:105012222190 |
| dc.identifier.isni.none.fl_str_mv |
0000 0001 2196 144X |
| identifier_str_mv |
10.11159/iccste25.189 23693002 International Conference on Civil Structural and Transportation Engineering 2-s2.0-105012222190 SCOPUS_ID:105012222190 0000 0001 2196 144X |
| url |
http://hdl.handle.net/10757/687659 |
| dc.language.iso.es_PE.fl_str_mv |
eng |
| language |
eng |
| dc.rights.es_PE.fl_str_mv |
info:eu-repo/semantics/openAccess |
| dc.rights.*.fl_str_mv |
Attribution 4.0 International |
| dc.rights.uri.*.fl_str_mv |
http://creativecommons.org/licenses/by/4.0/ |
| eu_rights_str_mv |
openAccess |
| rights_invalid_str_mv |
Attribution 4.0 International http://creativecommons.org/licenses/by/4.0/ |
| dc.format.es_PE.fl_str_mv |
application/pdf application/pdf |
| dc.publisher.es_PE.fl_str_mv |
Avestia Publishing |
| dc.source.none.fl_str_mv |
reponame:UPC-Institucional instname:Universidad Peruana de Ciencias Aplicadas instacron:UPC |
| instname_str |
Universidad Peruana de Ciencias Aplicadas |
| instacron_str |
UPC |
| institution |
UPC |
| reponame_str |
UPC-Institucional |
| collection |
UPC-Institucional |
| dc.source.journaltitle.none.fl_str_mv |
International Conference on Civil Structural and Transportation Engineering |
| bitstream.url.fl_str_mv |
https://repositorioacademico.upc.edu.pe/bitstream/10757/687659/3/license.txt https://repositorioacademico.upc.edu.pe/bitstream/10757/687659/2/license_rdf https://repositorioacademico.upc.edu.pe/bitstream/10757/687659/1/ICCSTE_189.pdf |
| bitstream.checksum.fl_str_mv |
8a4605be74aa9ea9d79846c1fba20a33 0175ea4a2d4caec4bbcc37e300941108 02e7e83f444d7ea54a9252da0749f6c1 |
| bitstream.checksumAlgorithm.fl_str_mv |
MD5 MD5 MD5 |
| repository.name.fl_str_mv |
Repositorio Académico UPC |
| repository.mail.fl_str_mv |
upc@openrepository.com |
| _version_ |
1852407021713752064 |
| spelling |
80d448a738429fcc6ab0e8059d17895a3000fb37fc1935ddf632070dce7624abe25300efe7732caddc3c3738cdc3aada37dfe8500Bazán, DarwinDíaz, LeonardoUlloa, Karem2025-12-16T00:42:42Z2025-12-16T00:42:42Z2025-01-0110.11159/iccste25.189http://hdl.handle.net/10757/68765923693002International Conference on Civil Structural and Transportation Engineering2-s2.0-105012222190SCOPUS_ID:1050122221900000 0001 2196 144XIn multifamily project construction, specialty subcontracting is common, but monitoring subcontractors, especially during finishing, presents significant challenges due to manual methods that are time consuming, make it difficult to detect deviations, and result in cost overruns and delays. This research proposes an automated monitoring procedure using a BIM model that integrates tools such as Revit, Navisworks, MS Project and Trimble Connect. The methodology includes four stages: analysis of information through surveys, identification of the traditional procedure in three companies, development of the new automated approach and validation in a pilot project. The results show a 42.4% reduction in daily monitoring time for subcontractors and a 41.4% reduction for technical personnel, in addition to improved access to real-time information. This optimizes coordination, reduces errors and ensures compliance with deadlines, significantly improving resource management in multifamily projects.application/pdfapplication/pdfengAvestia Publishinginfo:eu-repo/semantics/openAccessAttribution 4.0 Internationalhttp://creativecommons.org/licenses/by/4.0/BIMConstructionMonitoring timeProgress monitoringSubcontractorshttps://purl.org/pe-repo/ocde/ford#2.01.00Reducing Subcontractor Progress Monitoring Time on Multifamily Building Finishes Using a BIM-Based Procedureinfo:eu-repo/semantics/articleOtherInternational Conference on Civil Structural and Transportation Engineeringreponame:UPC-Institucionalinstname:Universidad Peruana de Ciencias Aplicadasinstacron:UPC2025-12-16T00:42:43ZLICENSElicense.txtlicense.txttext/plain; charset=utf-81748https://repositorioacademico.upc.edu.pe/bitstream/10757/687659/3/license.txt8a4605be74aa9ea9d79846c1fba20a33MD53falseCC-LICENSElicense_rdflicense_rdfapplication/rdf+xml; charset=utf-8908https://repositorioacademico.upc.edu.pe/bitstream/10757/687659/2/license_rdf0175ea4a2d4caec4bbcc37e300941108MD52falseORIGINALICCSTE_189.pdfICCSTE_189.pdfapplication/pdf2105454https://repositorioacademico.upc.edu.pe/bitstream/10757/687659/1/ICCSTE_189.pdf02e7e83f444d7ea54a9252da0749f6c1MD51true10757/687659oai:repositorioacademico.upc.edu.pe:10757/6876592025-12-16 00:42:43.52Repositorio Académico UPCupc@openrepository.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 |
| score |
13.449111 |
Nota importante:
La información contenida en este registro es de entera responsabilidad de la institución que gestiona el repositorio institucional donde esta contenido este documento o set de datos. El CONCYTEC no se hace responsable por los contenidos (publicaciones y/o datos) accesibles a través del Repositorio Nacional Digital de Ciencia, Tecnología e Innovación de Acceso Abierto (ALICIA).
La información contenida en este registro es de entera responsabilidad de la institución que gestiona el repositorio institucional donde esta contenido este documento o set de datos. El CONCYTEC no se hace responsable por los contenidos (publicaciones y/o datos) accesibles a través del Repositorio Nacional Digital de Ciencia, Tecnología e Innovación de Acceso Abierto (ALICIA).