Geological and geotechnical study in unconsolidated soils, for the installation of micropiles, in the Discharge Exit Tunnel at the San Gaban III Hydroelectric Plant, Carabaya – Puno

Descripción del Articulo

This research work is based on the problem of unconsolidated soils, which occurred in the excavation area of the 60-meter-long Discharge Exit tunnel, this tunnel was considered the most critical of the work due to the type of terrain and because the excavation was carried out below the Interoceanic...

Descripción completa

Detalles Bibliográficos
Autor: Zapata Castillo, Edwar Manuel
Formato: artículo
Fecha de Publicación:2023
Institución:Universidad Nacional Mayor de San Marcos
Repositorio:Revistas - Universidad Nacional Mayor de San Marcos
Lenguaje:español
OAI Identifier:oai:ojs.csi.unmsm:article/24535
Enlace del recurso:https://revistasinvestigacion.unmsm.edu.pe/index.php/iigeo/article/view/24535
Nivel de acceso:acceso abierto
Materia:Análisis numérico
Geomecánica en túneles
micropilotes
suelos cuaternarios
inyecciones de consolidación
Numerical analysis
Geomechanics in tunnels
Micropiles
Quaternary soils
Consolidation injections
Descripción
Sumario:This research work is based on the problem of unconsolidated soils, which occurred in the excavation area of the 60-meter-long Discharge Exit tunnel, this tunnel was considered the most critical of the work due to the type of terrain and because the excavation was carried out below the Interoceanic highway with encampané coverage of approximately 4.20 to 13.70 meters. The procedures that were performed; a numerical modeling to analyze the safety factor, three granulometry laboratory tests, three exploratory boreholes without core recovery and during the excavation according to each advance geomechanical evaluations and monitoring of deformations on the excavation surface, due to lithological and structural factors unfavorable in the work area, the excavation was carried out mechanically in three stages, vault and gables.According to the results of the numerical modeling, laboratory tests and surveys that were carried out, unfavorable lithological and structural factors were identified and due to these factors, umbrella-type micropiles injected with water and cement grout were installed to guarantee the stability of the tunnel before during and after excavation.
Nota importante:
La información contenida en este registro es de entera responsabilidad de la institución que gestiona el repositorio institucional donde esta contenido este documento o set de datos. El CONCYTEC no se hace responsable por los contenidos (publicaciones y/o datos) accesibles a través del Repositorio Nacional Digital de Ciencia, Tecnología e Innovación de Acceso Abierto (ALICIA).