Identification and evaluation of risks in the construction and implementation of the II-1 hospital in San Ignacio - Cajamarca

Descripción del Articulo

The research identified and assessed the risks in the execution of the construction and implementation project of the San Ignacio II-1 Hospital in Cajamarca in 2022, using the PMBOK Guide as a reference. Fifteen risks were identified, each with three root causes. A survey based on this guide was dev...

Descripción completa

Detalles Bibliográficos
Autores: Lizana Adrianzén, Alfredo, Rojas Adrianzén, Heidy
Formato: artículo
Fecha de Publicación:2024
Institución:Universidad Nacional de Jaén
Repositorio:Pakamuros
Lenguaje:español
OAI Identifier:oai:unj:article/354
Enlace del recurso:http://revistas.unj.edu.pe/index.php/pakamuros/article/view/354
Nivel de acceso:acceso abierto
Materia:Identificación de riesgos
evaluación de riesgos
construcción
Risk identification
risk assessment
construction
id REVUNJ_92ac264767dbcb59c0847a4f05225c22
oai_identifier_str oai:unj:article/354
network_acronym_str REVUNJ
network_name_str Pakamuros
repository_id_str
spelling Identification and evaluation of risks in the construction and implementation of the II-1 hospital in San Ignacio - CajamarcaIdentificación y evaluación de riesgos en la construcción e implementación del hospital II-1 de San Ignacio - CajamarcaLizana Adrianzén, AlfredoRojas Adrianzén, HeidyIdentificación de riesgosevaluación de riesgosconstrucciónRisk identificationrisk assessmentconstructionThe research identified and assessed the risks in the execution of the construction and implementation project of the San Ignacio II-1 Hospital in Cajamarca in 2022, using the PMBOK Guide as a reference. Fifteen risks were identified, each with three root causes. A survey based on this guide was developed and applied to a population of 50 previously trained project workers. The results showed that 93.33% of the risks were of high or moderate priority. Of the total risks, 6.66% were accepted, 46.67% were avoided, and 46.67% were mitigated. In addition, the prioritisation and response to the risks was linked, determining that 33.33% were remediable, 53.33% tolerable and 13.34% deferable. These findings showed the need for effective risk management strategies to ensure the viability and safety, recommending regular reviews and clear communication to reduce unforeseen events and ensure project success.La investigación identificó y evaluó los riesgos en la ejecución del proyecto de construcción e implementación del Hospital II-1 de San Ignacio en Cajamarca en 2022, utilizando como referencia la Guía del PMBOK. Se identificaron 15 riesgos, cada uno con tres causas generadoras. Se elaboró una encuesta basada en esta guía, aplicada a una población de 50 trabajadores del proyecto previamente capacitados. Los resultados mostraron que el 93.33% de los riesgos eran de alta o moderada prioridad. Del total de riesgos, el 6.66% se aceptaron, el 46.67% se evitaron y el 46.67% se mitigaron. Además, se relacionó la priorización y la respuesta a los riesgos, determinando que el 33.33% eran subsanables, el 53.33% tolerables y el 13.34% diferibles. Estos hallazgos exhibieron la necesidad de estrategias efectivas de gestión de riesgos para garantizar la viabilidad y seguridad, recomendando revisiones periódicas y una comunicación clara para reducir imprevistos y asegurar el éxito del proyecto.Universidad Nacional de Jaén2024-06-27info:eu-repo/semantics/articleinfo:eu-repo/semantics/publishedVersionapplication/pdftext/htmltext/xmlapplication/epub+ziptext/htmlhttp://revistas.unj.edu.pe/index.php/pakamuros/article/view/35410.37787/jw1a7762Pakamuros Scientific Journal; Vol. 12 No. 2 (2024): Revista Científica Pakamuros; 102 - 114Revista Científica Pakamuros; Vol. 12 Núm. 2 (2024): Revista Científica Pakamuros; 102 - 1142522-32402306-980510.37787/c4y2jd15reponame:Pakamurosinstname:Universidad Nacional de Jaéninstacron:UNJspahttp://revistas.unj.edu.pe/index.php/pakamuros/article/view/354/386http://revistas.unj.edu.pe/index.php/pakamuros/article/view/354/417http://revistas.unj.edu.pe/index.php/pakamuros/article/view/354/388http://revistas.unj.edu.pe/index.php/pakamuros/article/view/354/389http://revistas.unj.edu.pe/index.php/pakamuros/article/view/354/440Derechos de autor 2024 Revista Científica Pakamuroshttps://creativecommons.org/licenses/by-nc/4.0info:eu-repo/semantics/openAccessoai:unj:article/3542024-06-28T02:05:54Z
dc.title.none.fl_str_mv Identification and evaluation of risks in the construction and implementation of the II-1 hospital in San Ignacio - Cajamarca
Identificación y evaluación de riesgos en la construcción e implementación del hospital II-1 de San Ignacio - Cajamarca
title Identification and evaluation of risks in the construction and implementation of the II-1 hospital in San Ignacio - Cajamarca
spellingShingle Identification and evaluation of risks in the construction and implementation of the II-1 hospital in San Ignacio - Cajamarca
Lizana Adrianzén, Alfredo
Identificación de riesgos
evaluación de riesgos
construcción
Risk identification
risk assessment
construction
title_short Identification and evaluation of risks in the construction and implementation of the II-1 hospital in San Ignacio - Cajamarca
title_full Identification and evaluation of risks in the construction and implementation of the II-1 hospital in San Ignacio - Cajamarca
title_fullStr Identification and evaluation of risks in the construction and implementation of the II-1 hospital in San Ignacio - Cajamarca
title_full_unstemmed Identification and evaluation of risks in the construction and implementation of the II-1 hospital in San Ignacio - Cajamarca
title_sort Identification and evaluation of risks in the construction and implementation of the II-1 hospital in San Ignacio - Cajamarca
dc.creator.none.fl_str_mv Lizana Adrianzén, Alfredo
Rojas Adrianzén, Heidy
author Lizana Adrianzén, Alfredo
author_facet Lizana Adrianzén, Alfredo
Rojas Adrianzén, Heidy
author_role author
author2 Rojas Adrianzén, Heidy
author2_role author
dc.subject.none.fl_str_mv Identificación de riesgos
evaluación de riesgos
construcción
Risk identification
risk assessment
construction
topic Identificación de riesgos
evaluación de riesgos
construcción
Risk identification
risk assessment
construction
description The research identified and assessed the risks in the execution of the construction and implementation project of the San Ignacio II-1 Hospital in Cajamarca in 2022, using the PMBOK Guide as a reference. Fifteen risks were identified, each with three root causes. A survey based on this guide was developed and applied to a population of 50 previously trained project workers. The results showed that 93.33% of the risks were of high or moderate priority. Of the total risks, 6.66% were accepted, 46.67% were avoided, and 46.67% were mitigated. In addition, the prioritisation and response to the risks was linked, determining that 33.33% were remediable, 53.33% tolerable and 13.34% deferable. These findings showed the need for effective risk management strategies to ensure the viability and safety, recommending regular reviews and clear communication to reduce unforeseen events and ensure project success.
publishDate 2024
dc.date.none.fl_str_mv 2024-06-27
dc.type.none.fl_str_mv info:eu-repo/semantics/article
info:eu-repo/semantics/publishedVersion
format article
status_str publishedVersion
dc.identifier.none.fl_str_mv http://revistas.unj.edu.pe/index.php/pakamuros/article/view/354
10.37787/jw1a7762
url http://revistas.unj.edu.pe/index.php/pakamuros/article/view/354
identifier_str_mv 10.37787/jw1a7762
dc.language.none.fl_str_mv spa
language spa
dc.relation.none.fl_str_mv http://revistas.unj.edu.pe/index.php/pakamuros/article/view/354/386
http://revistas.unj.edu.pe/index.php/pakamuros/article/view/354/417
http://revistas.unj.edu.pe/index.php/pakamuros/article/view/354/388
http://revistas.unj.edu.pe/index.php/pakamuros/article/view/354/389
http://revistas.unj.edu.pe/index.php/pakamuros/article/view/354/440
dc.rights.none.fl_str_mv Derechos de autor 2024 Revista Científica Pakamuros
https://creativecommons.org/licenses/by-nc/4.0
info:eu-repo/semantics/openAccess
rights_invalid_str_mv Derechos de autor 2024 Revista Científica Pakamuros
https://creativecommons.org/licenses/by-nc/4.0
eu_rights_str_mv openAccess
dc.format.none.fl_str_mv application/pdf
text/html
text/xml
application/epub+zip
text/html
dc.publisher.none.fl_str_mv Universidad Nacional de Jaén
publisher.none.fl_str_mv Universidad Nacional de Jaén
dc.source.none.fl_str_mv Pakamuros Scientific Journal; Vol. 12 No. 2 (2024): Revista Científica Pakamuros; 102 - 114
Revista Científica Pakamuros; Vol. 12 Núm. 2 (2024): Revista Científica Pakamuros; 102 - 114
2522-3240
2306-9805
10.37787/c4y2jd15
reponame:Pakamuros
instname:Universidad Nacional de Jaén
instacron:UNJ
instname_str Universidad Nacional de Jaén
instacron_str UNJ
institution UNJ
reponame_str Pakamuros
collection Pakamuros
repository.name.fl_str_mv
repository.mail.fl_str_mv
_version_ 1846607484950675456
score 12.884314
Nota importante:
La información contenida en este registro es de entera responsabilidad de la institución que gestiona el repositorio institucional donde esta contenido este documento o set de datos. El CONCYTEC no se hace responsable por los contenidos (publicaciones y/o datos) accesibles a través del Repositorio Nacional Digital de Ciencia, Tecnología e Innovación de Acceso Abierto (ALICIA).