Mejora del proceso de producción de piezas industriales en la empresa SEFASI E.I.R.L mediante la técnica de las 5S y un plan de mantenimiento preventivo

Descripción del Articulo

The purpose of the research was to determine which activities do not add value to the product and create delays in the delivery process before its deadlines. To be able to determine this, a 5S plan will be implemented, as well as a preventive maintenance plan to the production line of the workshop,...

Descripción completa

Detalles Bibliográficos
Autores: Nuñez Castillo, Pablo Oscar, Perez Campos, Luis Jean Pierr
Formato: tesis de grado
Fecha de Publicación:2021
Institución:Universidad de Lima
Repositorio:ULIMA-Institucional
Lenguaje:español
OAI Identifier:oai:repositorio.ulima.edu.pe:20.500.12724/14315
Enlace del recurso:https://hdl.handle.net/20.500.12724/14315
Nivel de acceso:acceso abierto
Materia:Líneas de montaje
Administración de la producción
Estudio de tiempos
Assembly lines
Production management
Time study
https://purl.org/pe-repo/ocde/ford#2.11.04
id RULI_e1908f50a219b556ab5ebe01311cdaaf
oai_identifier_str oai:repositorio.ulima.edu.pe:20.500.12724/14315
network_acronym_str RULI
network_name_str ULIMA-Institucional
repository_id_str 3883
dc.title.es_PE.fl_str_mv Mejora del proceso de producción de piezas industriales en la empresa SEFASI E.I.R.L mediante la técnica de las 5S y un plan de mantenimiento preventivo
title Mejora del proceso de producción de piezas industriales en la empresa SEFASI E.I.R.L mediante la técnica de las 5S y un plan de mantenimiento preventivo
spellingShingle Mejora del proceso de producción de piezas industriales en la empresa SEFASI E.I.R.L mediante la técnica de las 5S y un plan de mantenimiento preventivo
Nuñez Castillo, Pablo Oscar
Líneas de montaje
Administración de la producción
Estudio de tiempos
Assembly lines
Production management
Time study
https://purl.org/pe-repo/ocde/ford#2.11.04
title_short Mejora del proceso de producción de piezas industriales en la empresa SEFASI E.I.R.L mediante la técnica de las 5S y un plan de mantenimiento preventivo
title_full Mejora del proceso de producción de piezas industriales en la empresa SEFASI E.I.R.L mediante la técnica de las 5S y un plan de mantenimiento preventivo
title_fullStr Mejora del proceso de producción de piezas industriales en la empresa SEFASI E.I.R.L mediante la técnica de las 5S y un plan de mantenimiento preventivo
title_full_unstemmed Mejora del proceso de producción de piezas industriales en la empresa SEFASI E.I.R.L mediante la técnica de las 5S y un plan de mantenimiento preventivo
title_sort Mejora del proceso de producción de piezas industriales en la empresa SEFASI E.I.R.L mediante la técnica de las 5S y un plan de mantenimiento preventivo
author Nuñez Castillo, Pablo Oscar
author_facet Nuñez Castillo, Pablo Oscar
Perez Campos, Luis Jean Pierr
author_role author
author2 Perez Campos, Luis Jean Pierr
author2_role author
dc.contributor.advisor.fl_str_mv Lizárraga Portugal, Carlos Augusto
dc.contributor.author.fl_str_mv Nuñez Castillo, Pablo Oscar
Perez Campos, Luis Jean Pierr
dc.subject.es_PE.fl_str_mv Líneas de montaje
Administración de la producción
Estudio de tiempos
Assembly lines
Production management
Time study
topic Líneas de montaje
Administración de la producción
Estudio de tiempos
Assembly lines
Production management
Time study
https://purl.org/pe-repo/ocde/ford#2.11.04
dc.subject.ocde.none.fl_str_mv https://purl.org/pe-repo/ocde/ford#2.11.04
description The purpose of the research was to determine which activities do not add value to the product and create delays in the delivery process before its deadlines. To be able to determine this, a 5S plan will be implemented, as well as a preventive maintenance plan to the production line of the workshop, this way we will guarantee the company’s sustainability in an extremely competitive market. The proposals to improve will be focused on the manufacturing of one of the most representative products of the company; however, the benefits will impact on the whole production line as well as the remaining products give the fact that they share the same workstations, and equipment among products. Additionally, a 13-month deadline will be set to implement the necessary tools to develop the 5S plan and the preventive maintenance for the production line. First, an analysis to determine the company’s current situation will take place. Starting from a Value Stream Mapping (VSM), followed by a cause-effect diagram to determine the main causes of the company’s troublesome. Finally, after identifying the main process losses, more improvement opportunities will be identified to employ the selected tools. As a consequence of the improvements, it is expected to reduce the quantity of activities that do not add value to the process to 30% and get machine availability to 90% as the reduction of the quantity of inoperative machine hours during the year. All of the above, will be joined by TIR > COK and an indicator benefit/cost more than 1.
publishDate 2021
dc.date.accessioned.none.fl_str_mv 2021-10-21T11:48:56Z
dc.date.available.none.fl_str_mv 2021-10-21T11:48:56Z
dc.date.issued.fl_str_mv 2021
dc.type.none.fl_str_mv info:eu-repo/semantics/bachelorThesis
dc.type.other.none.fl_str_mv Tesis
format bachelorThesis
dc.identifier.citation.es_PE.fl_str_mv Nuñez Castillo, P. O. y Perez Campos, L. J. P. (2021). Mejora del proceso de producción de piezas industriales en la empresa SEFASI E.I.R.L mediante la técnica de las 5S y un plan de mantenimiento preventivo [Tesis para optar el Título Profesional de Ingeniero Industrial, Universidad de Lima]. Repositorio institucional de la Universidad de Lima. https://hdl.handle.net/20.500.12724/14315
dc.identifier.uri.none.fl_str_mv https://hdl.handle.net/20.500.12724/14315
dc.identifier.isni.none.fl_str_mv 121541816
identifier_str_mv Nuñez Castillo, P. O. y Perez Campos, L. J. P. (2021). Mejora del proceso de producción de piezas industriales en la empresa SEFASI E.I.R.L mediante la técnica de las 5S y un plan de mantenimiento preventivo [Tesis para optar el Título Profesional de Ingeniero Industrial, Universidad de Lima]. Repositorio institucional de la Universidad de Lima. https://hdl.handle.net/20.500.12724/14315
121541816
url https://hdl.handle.net/20.500.12724/14315
dc.language.iso.none.fl_str_mv spa
language spa
dc.relation.ispartof.fl_str_mv SUNEDU
dc.rights.*.fl_str_mv info:eu-repo/semantics/openAccess
dc.rights.uri.*.fl_str_mv https://creativecommons.org/licenses/by-nc-sa/4.0/
eu_rights_str_mv openAccess
rights_invalid_str_mv https://creativecommons.org/licenses/by-nc-sa/4.0/
dc.format.none.fl_str_mv application/pdf
dc.publisher.none.fl_str_mv Universidad de Lima
dc.publisher.country.none.fl_str_mv PE
publisher.none.fl_str_mv Universidad de Lima
dc.source.none.fl_str_mv Repositorio Institucional - Ulima
Universidad de Lima
reponame:ULIMA-Institucional
instname:Universidad de Lima
instacron:ULIMA
instname_str Universidad de Lima
instacron_str ULIMA
institution ULIMA
reponame_str ULIMA-Institucional
collection ULIMA-Institucional
bitstream.url.fl_str_mv https://repositorio.ulima.edu.pe/bitstream/20.500.12724/14315/3/license.txt
https://repositorio.ulima.edu.pe/bitstream/20.500.12724/14315/4/Nu%c3%b1ez-Perez_Mejora-proceso-producci%c3%b3n.pdf.txt
https://repositorio.ulima.edu.pe/bitstream/20.500.12724/14315/2/license_rdf
https://repositorio.ulima.edu.pe/bitstream/20.500.12724/14315/1/Nu%c3%b1ez-Perez_Mejora-proceso-producci%c3%b3n.pdf
https://repositorio.ulima.edu.pe/bitstream/20.500.12724/14315/5/Nu%c3%b1ez-Perez_Mejora-proceso-producci%c3%b3n.pdf.jpg
bitstream.checksum.fl_str_mv 8a4605be74aa9ea9d79846c1fba20a33
b3d6876cb146c50193852f74f63acd47
8fc46f5e71650fd7adee84a69b9163c2
53bda65484d67bb42ad20bf064c32171
ca98df44c2a67798661cc78192d96e2e
bitstream.checksumAlgorithm.fl_str_mv MD5
MD5
MD5
MD5
MD5
repository.name.fl_str_mv Repositorio Universidad de Lima
repository.mail.fl_str_mv repositorio@ulima.edu.pe
_version_ 1847246187844861952
spelling Lizárraga Portugal, Carlos AugustoNuñez Castillo, Pablo OscarPerez Campos, Luis Jean Pierr2021-10-21T11:48:56Z2021-10-21T11:48:56Z2021Nuñez Castillo, P. O. y Perez Campos, L. J. P. (2021). Mejora del proceso de producción de piezas industriales en la empresa SEFASI E.I.R.L mediante la técnica de las 5S y un plan de mantenimiento preventivo [Tesis para optar el Título Profesional de Ingeniero Industrial, Universidad de Lima]. Repositorio institucional de la Universidad de Lima. https://hdl.handle.net/20.500.12724/14315https://hdl.handle.net/20.500.12724/14315121541816The purpose of the research was to determine which activities do not add value to the product and create delays in the delivery process before its deadlines. To be able to determine this, a 5S plan will be implemented, as well as a preventive maintenance plan to the production line of the workshop, this way we will guarantee the company’s sustainability in an extremely competitive market. The proposals to improve will be focused on the manufacturing of one of the most representative products of the company; however, the benefits will impact on the whole production line as well as the remaining products give the fact that they share the same workstations, and equipment among products. Additionally, a 13-month deadline will be set to implement the necessary tools to develop the 5S plan and the preventive maintenance for the production line. First, an analysis to determine the company’s current situation will take place. Starting from a Value Stream Mapping (VSM), followed by a cause-effect diagram to determine the main causes of the company’s troublesome. Finally, after identifying the main process losses, more improvement opportunities will be identified to employ the selected tools. As a consequence of the improvements, it is expected to reduce the quantity of activities that do not add value to the process to 30% and get machine availability to 90% as the reduction of the quantity of inoperative machine hours during the year. All of the above, will be joined by TIR > COK and an indicator benefit/cost more than 1.El presente trabajo tiene como objetivo disminuir las actividades que no añaden valor al producto y generan retrasos en la entrega de los pedidos de piezas industriales dentro de los plazos establecidos, esto se busca conseguir a partir de la implementación la técnica de 5S; así como, un plan de mantenimiento preventivo, garantizando de esta forma la sostenibilidad de la empresa dentro de un mercado sumamente competitivo. El alcance de las propuestas de mejora se enfocará en la fabricación de uno de los productos más representativos de la empresa, no obstante, los beneficios impactarán en toda la línea de producción, así como, en el resto de productos fabricados en el taller, ya que comparten las mismas estaciones de trabajo y maquinaria entre un producto y otro. Así mismo, se destinará el plazo de 3 meses, para la implementación de las herramientas necesarias para el desarrollo del plan piloto de 5S y plan de mantenimiento preventivo. Lo primero que se realizará será el análisis de la situación actual de la empresa, el cual partirá de la técnica de Mapa de Flujo del Valor (VSM) actual, seguido por diagrama causa-efecto, determinado las causas raíces de la problemática en la empresa, finalmente, se dará enfoque a aquellas causas seleccionadas como las más críticas. Por otro lado, identificado las principales pérdidas del proceso, se procederán a identificar las oportunidades de mejora en las que se emplearán las herramientas seleccionadas. Como consecuencia de las mejoras implementadas, se espera reducir las actividades que no agregan valor al proceso al 30% y contar con una disponibilidad de máquina del 90%; así mismo, reducir a 470 la cantidad de minutos perdidos por parada no prevista de máquina a la semana. Todo esto acompañado de un TIR > COK y un indicador Beneficio/Costo mayor a 1.application/pdfspaUniversidad de LimaPEinfo:eu-repo/semantics/openAccesshttps://creativecommons.org/licenses/by-nc-sa/4.0/Repositorio Institucional - UlimaUniversidad de Limareponame:ULIMA-Institucionalinstname:Universidad de Limainstacron:ULIMALíneas de montajeAdministración de la producciónEstudio de tiemposAssembly linesProduction managementTime studyhttps://purl.org/pe-repo/ocde/ford#2.11.04Mejora del proceso de producción de piezas industriales en la empresa SEFASI E.I.R.L mediante la técnica de las 5S y un plan de mantenimiento preventivoinfo:eu-repo/semantics/bachelorThesisTesisSUNEDUTítulo ProfesionalIngeniería IndustrialUniversidad de Lima. Facultad de Ingeniería y ArquitecturaIngeniero Industrialhttps://orcid.org/0000-0002-7057-4099436913527220264685036648007635https://purl.org/pe-repo/renati/level#tituloProfesionalSotomayor Cabrera, ArístidesReaño Vera, Abel Antonio MartinGálvez Zárate, Carloshttps://purl.org/pe-repo/renati/type#tesisOILICENSElicense.txtlicense.txttext/plain; charset=utf-81748https://repositorio.ulima.edu.pe/bitstream/20.500.12724/14315/3/license.txt8a4605be74aa9ea9d79846c1fba20a33MD53TEXTNuñez-Perez_Mejora-proceso-producción.pdf.txtNuñez-Perez_Mejora-proceso-producción.pdf.txtExtracted texttext/plain110191https://repositorio.ulima.edu.pe/bitstream/20.500.12724/14315/4/Nu%c3%b1ez-Perez_Mejora-proceso-producci%c3%b3n.pdf.txtb3d6876cb146c50193852f74f63acd47MD54CC-LICENSElicense_rdflicense_rdfapplication/rdf+xml; charset=utf-81037https://repositorio.ulima.edu.pe/bitstream/20.500.12724/14315/2/license_rdf8fc46f5e71650fd7adee84a69b9163c2MD52ORIGINALNuñez-Perez_Mejora-proceso-producción.pdfNuñez-Perez_Mejora-proceso-producción.pdfTesisapplication/pdf1595526https://repositorio.ulima.edu.pe/bitstream/20.500.12724/14315/1/Nu%c3%b1ez-Perez_Mejora-proceso-producci%c3%b3n.pdf53bda65484d67bb42ad20bf064c32171MD51THUMBNAILNuñez-Perez_Mejora-proceso-producción.pdf.jpgNuñez-Perez_Mejora-proceso-producción.pdf.jpgGenerated Thumbnailimage/jpeg12071https://repositorio.ulima.edu.pe/bitstream/20.500.12724/14315/5/Nu%c3%b1ez-Perez_Mejora-proceso-producci%c3%b3n.pdf.jpgca98df44c2a67798661cc78192d96e2eMD5520.500.12724/14315oai:repositorio.ulima.edu.pe:20.500.12724/143152025-09-17 13:55:03.614Repositorio Universidad de Limarepositorio@ulima.edu.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
score 12.883251
Nota importante:
La información contenida en este registro es de entera responsabilidad de la institución que gestiona el repositorio institucional donde esta contenido este documento o set de datos. El CONCYTEC no se hace responsable por los contenidos (publicaciones y/o datos) accesibles a través del Repositorio Nacional Digital de Ciencia, Tecnología e Innovación de Acceso Abierto (ALICIA).