Infrastructure projects incorporate, as a general rule, a complex contractual structure that must respond to the needs of the project, including the risk management in the construction of the works.The objective is to develop a risk management model that improves the scope, time and cost of the dire...

Descripción completa

Detalles Bibliográficos
Autores: Quevedo Porras, Violeta Zarela, Salgado Canal, José Antonio
Formato: artículo
Fecha de Publicación:2020
Institución:Universidad Privada de Tacna
Repositorio:Revistas - Universidad Privada de Tacna
Lenguaje:español
OAI Identifier:oai:revistas.upt.edu.pe:article/138
Enlace del recurso:https://revistas.upt.edu.pe/ojs/index.php/vestsc/article/view/138
Nivel de acceso:acceso abierto
Materia:Riesgos
Alcance
Tiempo
Costo
Risks
Scope
Time
Cost
id REVUPT_36280bb2c4f4dbe0f863a7ece5ace648
oai_identifier_str oai:revistas.upt.edu.pe:article/138
network_acronym_str REVUPT
network_name_str Revistas - Universidad Privada de Tacna
repository_id_str
spelling Risk management model and its impact on the scope, time and cost of basic sanitation projects, case Tacna, 2017Modelo de gestión de riesgos y su impacto en el alcance, tiempo y costo de proyectos de saneamiento básico, caso Tacna, 2017.Quevedo Porras, Violeta ZarelaSalgado Canal, José AntonioRiesgosAlcanceTiempoCostoRisksScopeTimeCostInfrastructure projects incorporate, as a general rule, a complex contractual structure that must respond to the needs of the project, including the risk management in the construction of the works.The objective is to develop a risk management model that improves the scope, time and cost of the direct management basic sanitation projects executed by the EPS of the Tacna Region, 2017. For this purpose, the research used is of the application type. , not experimental and quantitative. Determine the specific objectives through tools and techniques, through surveys and expert evaluation, which are processed with the Monte Carlo Method using the RiskyProject Professional Program that records the risks that are part of the scope, determines the contingency in cost and time.The risk management model to be followed responds to the good practices of the PMBOK. The application of the proposed model improves the execution of basic sanitation projects in the Tacna Region, allowing compliance with the scope, deadline, economic profitability and sustainable development.Los proyectos de infraestructura incorporan como regla general, una estructura contractual compleja que debe responder a las necesidades del proyecto, incluyendo la gestión del riesgo en la construcción de las obras. Se tiene como objetivo desarrollar un modelo de gestión de riesgos que mejore el alcance, tiempo y costo en los proyectos de saneamiento básico de administración directa ejecutados por la EPS de la Región de Tacna, 2017. Para este fin la investigación utilizada es de tipo aplicativa, no experimental y cuantitativa. Determina los objetivos específicos mediante herramientas y técnicas, por medio de encuestas y evaluación de expertos, que son procesados con el Método de Monte Carlo utilizando el Programa RiskyProject Professional que registra los riesgos que forman parte del alcance, determina la contingencia en costo y tiempo. El modelo de gestión de riesgos a seguir, responde a las buenas prácticas del PMBOK. La aplicación del modelo propuesto mejora la ejecución de proyectos de saneamiento básico de la Región de Tacna permitiendo el cumplimiento del alcance, plazo, una rentabilidad económica y el desarrollo sostenible.Universidad Privada de Tacna2020-01-22info:eu-repo/semantics/articleinfo:eu-repo/semantics/publishedVersionapplication/pdfhttps://revistas.upt.edu.pe/ojs/index.php/vestsc/article/view/13810.47796/ves.v8i2.138REVISTA VERITAS ET SCIENTIA - UPT; Vol. 8 No. 2 (2019): Veritas et Scientia; pp. 1211 - 1219REVISTA VERITAS ET SCIENTIA - UPT; Vol. 8 Núm. 2 (2019): Veritas et Scientia; pp. 1211 - 12192617-06392307-513910.47796/ves.v8i2reponame:Revistas - Universidad Privada de Tacnainstname:Universidad Privada de Tacnainstacron:UPTspahttps://revistas.upt.edu.pe/ojs/index.php/vestsc/article/view/138/123info:eu-repo/semantics/openAccessoai:revistas.upt.edu.pe:article/1382021-07-12T18:02:13Z
dc.title.none.fl_str_mv Risk management model and its impact on the scope, time and cost of basic sanitation projects, case Tacna, 2017
Modelo de gestión de riesgos y su impacto en el alcance, tiempo y costo de proyectos de saneamiento básico, caso Tacna, 2017.
title Risk management model and its impact on the scope, time and cost of basic sanitation projects, case Tacna, 2017
spellingShingle Risk management model and its impact on the scope, time and cost of basic sanitation projects, case Tacna, 2017
Quevedo Porras, Violeta Zarela
Riesgos
Alcance
Tiempo
Costo
Risks
Scope
Time
Cost
title_short Risk management model and its impact on the scope, time and cost of basic sanitation projects, case Tacna, 2017
title_full Risk management model and its impact on the scope, time and cost of basic sanitation projects, case Tacna, 2017
title_fullStr Risk management model and its impact on the scope, time and cost of basic sanitation projects, case Tacna, 2017
title_full_unstemmed Risk management model and its impact on the scope, time and cost of basic sanitation projects, case Tacna, 2017
title_sort Risk management model and its impact on the scope, time and cost of basic sanitation projects, case Tacna, 2017
dc.creator.none.fl_str_mv Quevedo Porras, Violeta Zarela
Salgado Canal, José Antonio
author Quevedo Porras, Violeta Zarela
author_facet Quevedo Porras, Violeta Zarela
Salgado Canal, José Antonio
author_role author
author2 Salgado Canal, José Antonio
author2_role author
dc.subject.none.fl_str_mv Riesgos
Alcance
Tiempo
Costo
Risks
Scope
Time
Cost
topic Riesgos
Alcance
Tiempo
Costo
Risks
Scope
Time
Cost
description Infrastructure projects incorporate, as a general rule, a complex contractual structure that must respond to the needs of the project, including the risk management in the construction of the works.The objective is to develop a risk management model that improves the scope, time and cost of the direct management basic sanitation projects executed by the EPS of the Tacna Region, 2017. For this purpose, the research used is of the application type. , not experimental and quantitative. Determine the specific objectives through tools and techniques, through surveys and expert evaluation, which are processed with the Monte Carlo Method using the RiskyProject Professional Program that records the risks that are part of the scope, determines the contingency in cost and time.The risk management model to be followed responds to the good practices of the PMBOK. The application of the proposed model improves the execution of basic sanitation projects in the Tacna Region, allowing compliance with the scope, deadline, economic profitability and sustainable development.
publishDate 2020
dc.date.none.fl_str_mv 2020-01-22
dc.type.none.fl_str_mv info:eu-repo/semantics/article
info:eu-repo/semantics/publishedVersion
format article
status_str publishedVersion
dc.identifier.none.fl_str_mv https://revistas.upt.edu.pe/ojs/index.php/vestsc/article/view/138
10.47796/ves.v8i2.138
url https://revistas.upt.edu.pe/ojs/index.php/vestsc/article/view/138
identifier_str_mv 10.47796/ves.v8i2.138
dc.language.none.fl_str_mv spa
language spa
dc.relation.none.fl_str_mv https://revistas.upt.edu.pe/ojs/index.php/vestsc/article/view/138/123
dc.rights.none.fl_str_mv info:eu-repo/semantics/openAccess
eu_rights_str_mv openAccess
dc.format.none.fl_str_mv application/pdf
dc.publisher.none.fl_str_mv Universidad Privada de Tacna
publisher.none.fl_str_mv Universidad Privada de Tacna
dc.source.none.fl_str_mv REVISTA VERITAS ET SCIENTIA - UPT; Vol. 8 No. 2 (2019): Veritas et Scientia; pp. 1211 - 1219
REVISTA VERITAS ET SCIENTIA - UPT; Vol. 8 Núm. 2 (2019): Veritas et Scientia; pp. 1211 - 1219
2617-0639
2307-5139
10.47796/ves.v8i2
reponame:Revistas - Universidad Privada de Tacna
instname:Universidad Privada de Tacna
instacron:UPT
instname_str Universidad Privada de Tacna
instacron_str UPT
institution UPT
reponame_str Revistas - Universidad Privada de Tacna
collection Revistas - Universidad Privada de Tacna
repository.name.fl_str_mv
repository.mail.fl_str_mv
_version_ 1844255145205956608
score 13.049697
Nota importante:
La información contenida en este registro es de entera responsabilidad de la institución que gestiona el repositorio institucional donde esta contenido este documento o set de datos. El CONCYTEC no se hace responsable por los contenidos (publicaciones y/o datos) accesibles a través del Repositorio Nacional Digital de Ciencia, Tecnología e Innovación de Acceso Abierto (ALICIA).