The excessive use of force majeure for the extension of Deadlines in electric sector projects

Descripción del Articulo

During the last decade, the failure to meet public works execution deadlines has been a frequent matter. Particularly among the electricity sector, private companies have loosened established project execution deadlines by resorting to force majeure as a justifica...

Descripción completa

Detalles Bibliográficos
Autor: Aguirre Ramírez, Mayra
Formato: artículo
Fecha de Publicación:2019
Institución:Pontificia Universidad Católica del Perú
Repositorio:Revistas - Pontificia Universidad Católica del Perú
Lenguaje:español
OAI Identifier:oai:ojs.pkp.sfu.ca:article/21233
Enlace del recurso:http://revistas.pucp.edu.pe/index.php/themis/article/view/21233
Nivel de acceso:acceso abierto
Materia:Force majeure
electric energy concessions
public-private partnerships
electric concessions law
commercial start-up date
Fuerza mayor
concesiones eléctricas
Asociaciones Público-Privadas
Ley de Concesiones Eléctricas (LCE)
fecha de Puesta en Operación Comercial (POC)
id REVPUCP_5a8f18d8d028d0584cf8753f157f924e
oai_identifier_str oai:ojs.pkp.sfu.ca:article/21233
network_acronym_str REVPUCP
network_name_str Revistas - Pontificia Universidad Católica del Perú
repository_id_str
spelling The excessive use of force majeure for the extension of Deadlines in electric sector projectsEl excesivo uso de la fuerza mayor para la ampliación de plazos en proyectos del sector eléctricoAguirre Ramírez, MayraForce majeureelectric energy concessionspublic-private partnershipselectric concessions lawcommercial start-up dateFuerza mayorconcesiones eléctricasAsociaciones Público-PrivadasLey de Concesiones Eléctricas (LCE)fecha de Puesta en Operación Comercial (POC)During the last decade, the failure to meet public works execution deadlines has been a frequent matter. Particularly among the electricity sector, private companies have loosened established project execution deadlines by resorting to force majeure as a justification for obtaining an extended deadline. However, have these granted extensions really been justified in events of force majeure?.In this article, the author explains the regimes under which electric concessions are granted to further detail the regulation established electric project deadlines and the consequences of its non-compliance. Subsequently, the author reviews the regulation and doctrine on force majeure and lastly, acutely analyzes its use as justification in the deadline extensions granted in recent years.El incumplimiento de plazos en la ejecución de obras públicas ha sido frecuente en la última década. Particularmente en el sector eléctrico, las empresas privadas han logrado flexibilizar los plazos establecidos para la ejecución de proyectos, recurriendo a la fuerza mayor como justificación para obtener una prórroga. Pero, ¿realmente las prórrogas otorgadas se justifican en eventos de fuerza mayor?.En este artículo, la autora explica los regímenes bajo los que se otorgan las concesiones eléctricas para luego, detallar la regulación de los plazos establecidos para los proyectos y las consecuencias de incumplirlos. Posteriormente, revisa la regulación y doctrina sobre la fuerza mayor y finaliza analizando críticamente su uso como justificación en las prórrogas concedidas en los últimos años.Pontificia Universidad Católica del Perú2019-10-15info:eu-repo/semantics/articleinfo:eu-repo/semantics/publishedVersionapplication/pdfhttp://revistas.pucp.edu.pe/index.php/themis/article/view/21233THEMIS Revista de Derecho; Núm. 74 (2018): Derecho Ambiental; 55-751810-9934reponame:Revistas - Pontificia Universidad Católica del Perúinstname:Pontificia Universidad Católica del Perúinstacron:PUCPspahttp://revistas.pucp.edu.pe/index.php/themis/article/view/21233/20936Derechos de autor 2019 TH?MIS-Revista de Derechoinfo:eu-repo/semantics/openAccessoai:ojs.pkp.sfu.ca:article/212332021-02-17T16:10:25Z
dc.title.none.fl_str_mv The excessive use of force majeure for the extension of Deadlines in electric sector projects
El excesivo uso de la fuerza mayor para la ampliación de plazos en proyectos del sector eléctrico
title The excessive use of force majeure for the extension of Deadlines in electric sector projects
spellingShingle The excessive use of force majeure for the extension of Deadlines in electric sector projects
Aguirre Ramírez, Mayra
Force majeure
electric energy concessions
public-private partnerships
electric concessions law
commercial start-up date
Fuerza mayor
concesiones eléctricas
Asociaciones Público-Privadas
Ley de Concesiones Eléctricas (LCE)
fecha de Puesta en Operación Comercial (POC)
title_short The excessive use of force majeure for the extension of Deadlines in electric sector projects
title_full The excessive use of force majeure for the extension of Deadlines in electric sector projects
title_fullStr The excessive use of force majeure for the extension of Deadlines in electric sector projects
title_full_unstemmed The excessive use of force majeure for the extension of Deadlines in electric sector projects
title_sort The excessive use of force majeure for the extension of Deadlines in electric sector projects
dc.creator.none.fl_str_mv Aguirre Ramírez, Mayra
author Aguirre Ramírez, Mayra
author_facet Aguirre Ramírez, Mayra
author_role author
dc.subject.none.fl_str_mv Force majeure
electric energy concessions
public-private partnerships
electric concessions law
commercial start-up date
Fuerza mayor
concesiones eléctricas
Asociaciones Público-Privadas
Ley de Concesiones Eléctricas (LCE)
fecha de Puesta en Operación Comercial (POC)
topic Force majeure
electric energy concessions
public-private partnerships
electric concessions law
commercial start-up date
Fuerza mayor
concesiones eléctricas
Asociaciones Público-Privadas
Ley de Concesiones Eléctricas (LCE)
fecha de Puesta en Operación Comercial (POC)
description During the last decade, the failure to meet public works execution deadlines has been a frequent matter. Particularly among the electricity sector, private companies have loosened established project execution deadlines by resorting to force majeure as a justification for obtaining an extended deadline. However, have these granted extensions really been justified in events of force majeure?.In this article, the author explains the regimes under which electric concessions are granted to further detail the regulation established electric project deadlines and the consequences of its non-compliance. Subsequently, the author reviews the regulation and doctrine on force majeure and lastly, acutely analyzes its use as justification in the deadline extensions granted in recent years.
publishDate 2019
dc.date.none.fl_str_mv 2019-10-15
dc.type.none.fl_str_mv info:eu-repo/semantics/article
info:eu-repo/semantics/publishedVersion
format article
status_str publishedVersion
dc.identifier.none.fl_str_mv http://revistas.pucp.edu.pe/index.php/themis/article/view/21233
url http://revistas.pucp.edu.pe/index.php/themis/article/view/21233
dc.language.none.fl_str_mv spa
language spa
dc.relation.none.fl_str_mv http://revistas.pucp.edu.pe/index.php/themis/article/view/21233/20936
dc.rights.none.fl_str_mv Derechos de autor 2019 TH?MIS-Revista de Derecho
info:eu-repo/semantics/openAccess
rights_invalid_str_mv Derechos de autor 2019 TH?MIS-Revista de Derecho
eu_rights_str_mv openAccess
dc.format.none.fl_str_mv application/pdf
dc.publisher.none.fl_str_mv Pontificia Universidad Católica del Perú
publisher.none.fl_str_mv Pontificia Universidad Católica del Perú
dc.source.none.fl_str_mv THEMIS Revista de Derecho; Núm. 74 (2018): Derecho Ambiental; 55-75
1810-9934
reponame:Revistas - Pontificia Universidad Católica del Perú
instname:Pontificia Universidad Católica del Perú
instacron:PUCP
instname_str Pontificia Universidad Católica del Perú
instacron_str PUCP
institution PUCP
reponame_str Revistas - Pontificia Universidad Católica del Perú
collection Revistas - Pontificia Universidad Católica del Perú
repository.name.fl_str_mv
repository.mail.fl_str_mv
_version_ 1841536838121029632
score 13.772021
Nota importante:
La información contenida en este registro es de entera responsabilidad de la institución que gestiona el repositorio institucional donde esta contenido este documento o set de datos. El CONCYTEC no se hace responsable por los contenidos (publicaciones y/o datos) accesibles a través del Repositorio Nacional Digital de Ciencia, Tecnología e Innovación de Acceso Abierto (ALICIA).